Question 13 Reducing Project Duration Duration Project Optimal Point Max Score 2 Total Pro Q29228829

Question 13 When reducing project duration, the duration for a project that is optimal is at the point where: Max score: 2 Total project costs are the lowest Indirect costs are the lowest Direct costs are the lowest. Direct costs equal indirect costs The project changes from time-constrained to resource-constrained. Next question Previous questionQuestion 13 When reducing project duration, the duration for a project that is optimal is at the point where: Max score: 2 Total project costs are the lowest Indirect costs are the lowest Direct costs are the lowest. Direct costs equal indirect costs The project changes from time-constrained to resource-constrained. Next question Previous question Show transcribed image text