A project is in the middle of the executing effort when a stakeholder suggests a change that would result in the third major

A project is in the middle of the executing effort when a stakeholder suggests a change that would result in the third major overhaul of the project. At the same time, the project manager discovers that a large work package was not completed because a team member’s manager moved her to another project that had a higher priority. Of the following, who is the best person for the project manager to address these issues with? The team. The sponsor. Senior management. The customer. Show transcribed image text