Project Description New Computer Controlled Conveyor Belt Exciting Project Moves Positions Q29009159
Project Description
The new computer-controlled conveyor belt is an exciting projectthat moves and positions items on the conveyor belt within 1millimeter. The project will produce a new system for futureinstallations, and for replacement of those in the field, at a lowcost. The computer-controlled conveyor belt has the potential to bea critical unit in 30 percent of the systems installed infactories. The new system is also easier to update with futuretechnologies. Table 1 has been developed for you to use incompleting the project exercises.
Table 1 Conveyor Belt Project;WBS
Hardware
Hardware specifications
Hardware design
Hardware documentation
Prototypes
Order circuit boards
Assemble preproduction models
Operating system
Kernel specifications
Drivers
Disk drivers
Serial I/O drivers
Memory management
Operating system documentation
Network interface
Utilities
Utilities specifications
Routine utilities
Complex utilities
Utilities documentation
Shell
System integration
Architectural decisions
Integration first phase
System hard/software test
Project documentation
Integration acceptance testing
The project begins January 4, 2010.
The following holidays are observed: January 1, Memorial Day(last Monday in May), July 4th, Labor Day (first Mondayin September), Thanksgiving Day (4th Thursday in November),December 25 and 26.
If a holiday falls on a Saturday then Friday will be given as anextra day off, and if it falls on a Sunday, then Monday will begiven as a day off.
The project teams work eight-hour days, Monday throughFriday.
Table 2 Conveyor BeltProject; Schedule
Activity
Description
Resource (one team each)
Duration (days)
Preceding Activity
1
Architectural decisions
Design
25
—
2
Hardware specifications
Development, design
50
1
3
Kernel specifications
Design
20
1
4
Utilities specifications
Development, design
15
1
5
Hardware design
Design, development
70
2
6
Disk drivers
Assembly, development
100
3
7
Memory management
Development
90
3
8
Operating system documentation
Design, documentation
25
3
9
Routine utilities
Development
60
4
10
Complex utilities
Development
80
4
11
Utilities documentation
Documentation, design
20
4
12
Hardware documentation
Documentation, design
30
5
13
Integration first phase
Assembly, development
50
6,7,8,9,10,11,12
14
Prototypes
Assembly, development
80
13
15
Serial I/O drivers
Development
130
13
16
System hard/software test
Assembly
25
14,15
17
Order circuit boards
Purchasing
5
16
18
Network interface
Development
90
16
19
Shell
Development
60
16
20
Project documentation
Documentation, development
50
16
21
Assemble preproduction models
Assembly, development
30
17F-S, lag 50 days
22
Integrated acceptance testing
Assembly, development
60
18,19,20,21
Table 3 OrganizationResources
Name
Group
Cost ($/hr)
Design
R&D (2 teams)
$100
Development
R&D (2 teams)
70
Documentation
R&D (1 team)
60
Assembly/test
R&D (1 team)
70
Purchasing
Procurement (1 team)
40
Part 3 (Bonus)
Prepare status reports for the fourth quarter of the project(Fourth Quarter, January 1, 2011) given theinformation provided in Table 4. This requires saving your resourceschedule as a base- line and inserting the appropriate statusreport date in the program. Assume that no work has been completedon the day of the status report.
Your status report should include a table containing the PV, EV,AC, BAC, EAC, SV, CV, and CPI for each activity and the wholeproject. The report should also address the followingquestions:
How is the project progressing in terms of cost andschedule?
What activities have gone well? What activities have not gonewell?
What do the PCIB and PCIC indicate in terms of how much of theproject has been accomplished to date?
What is the forecasted cost at completion (EACf)? What is thepredicted VACf ?
Report and interpret the TCPI for the project at this point intime.
What is the estimated date of completion?
Table 4 January 1,2011
Activity
Start Date
Finish Date
Actual Duration
Remaining Duration
Hardware specifications
2/9/10
4/12/10
45
0
Hardware design
4/13/10
7/16/10
67
0
Hardware documentation
7/19/10
8/24/10
27
0
Prototypes
11/11/10
–
34
44
Kernel specifications
2/8/10
3/12/10
25
0
Disk drivers
3/15/10
8/17/10
110
0
Serial I/O drivers
11/11/10
–
34
119
Memory management
3/15/10
7/30/10
98
0
Op. systems documentation
3/15/10
4/16/10
25
0
Utilities specifications
3/8/10
3/29/10
16
0
Routine utilities
4/26/10
7/27/10
65
0
Complex utilities
3/30/10
8/11/10
95
0
Utilities documentation
5/3/10
6/2/10
22
0
Architectural decisions
1/4/10
2/5/10
25
0
Integration 1st phase
8/25/10
11/10/10
55
0
Part 4
You have received revised estimates for the remaining activitiesat the end of the fourth quarter:
Prototypes will be completed on 3/8/11.
Serial I/O drivers will be completed on 6/30/11.
System hardware/software test will start on 7/1/11 and take 25days.
Order circuit boards will start on 8/8/11 and take 5 days.
Assemble preproduction model will begin on 10/14/11 and take 18days.
Project documentation is expected to start on 8/8/11 and willtake 55 days.
Network interface is expected to start on 8/8/11 and will take99 days.
Shell is expected to start on 8/8/11 and will take 55 days.
Integrated acceptance testing is expected to start on 12/29/11and will take 54 days.
Prepare a memo that addresses the following questions:
What is the new EAC for the project? How long should the projecttake given these revised estimates?
What recommendations would you make?
Include a revised schedule, a Tracking Gantt chart, and costtable with your memo.
Leave a Reply
Want to join the discussion?Feel free to contribute!