Problem 9-10

In the following MRP planning schedule for Item J, indicate thecorrect net requirements, planned order receipts, and planned orderreleases to meet the gross requirements. Lead time is one week.(Leave no cells blank – be certain to enter “0” whereverrequired.)

WEEK NUMBER

ITEM J012345Gross requirements704565On hand30Net requirementsPlanned order receiptPlanned order release

Period12345Item J
LT = 1
Q = L4LGross requirements704565Scheduled receiptsProjected available balanceNet requirementsPlanned order receiptsPlanned order releases