Problem 9 10 Following Mrp Planning Schedule Item J Indicate Correct Net Requirements Plan Q36034757
Problem 9-10
In the following MRP planning schedule for Item J, indicate thecorrect net requirements, planned order receipts, and planned orderreleases to meet the gross requirements. Lead time is one week.(Leave no cells blank – be certain to enter “0” whereverrequired.)
WEEK NUMBER
ITEM J012345Gross requirements704565On hand30Net requirementsPlanned order receiptPlanned order release
Period12345Item J
LT = 1
Q = L4LGross requirements704565Scheduled receiptsProjected available balanceNet requirementsPlanned order receiptsPlanned order releases
Leave a Reply
Want to join the discussion?Feel free to contribute!