Problem 4: Building a car goes through several processes as follows: B, C D. E Available production time 100 hours/week Production target 50 units/week What is the required cycle time? What is the theoretical minimum number of stations? b) What tasks should be assigned to which stations? # Assigned Tasks Task time idle time d) Which station is the bottleneck? e What is the actual number of stations? What is the efficiency? p) What is the utilization of each Station? Station 1: Station 2 Show transcribed image text