A sawmill runs for three 4-hour shifts per day. it produces 500 2×4’s

A sawmill runs for three 4-hour shifts per day. It produces 500 2×4’s per hour, which are divided into 50 piece bundles automatically. If a forklift operator is able to load 10 bundles of 2×4’s per hour, how many hours will it take the operator to load a full day of production